Gold extraction plant construction project
The objective of the present project is to establish a gold recovery plant with an annual production capacity of approximately 442.5 kilograms of gold bars with a purity of 99.99%. The Madofti Gold Mine is located in the Baluchistan region of Sistan and Baluchestan Province, approximately 100 kilometers south-southeast of Zahedan and about 7 kilometers northwest of Mount Taftan. Given that a significant portion of the country’s gold demand is…
The objective of the present project is to establish a gold recovery plant with an annual production capacity of approximately 442.5 kilograms of gold bars with a purity of 99.99%. The Madofti Gold Mine is located in the Baluchistan region of Sistan and Baluchestan Province, approximately 100 kilometers south-southeast of Zahedan and about 7 kilometers northwest of Mount Taftan.
Given that a significant portion of the country’s gold demand is currently met through imports, improving production technologies in this field is expected to facilitate the efficient exploitation of Iran’s gold reserves and increase the grade and quality of domestically produced gold. In this regard, Pars Tamin Mining Development Company, equipped with advanced technology, has the capability to efficiently exploit high-grade gold resources in the Taftan region of Sistan and Baluchestan Province. In addition to supporting the medium-term objectives of the industry, the project will contribute to economic development and job creation in the region.
Construction and implementation of the gold recovery unit commenced in the first half of 2022. Taking into account unforeseen delays, gold production and commercial supply were scheduled to commence in the second half of 2023. The production plan envisages operating at 80% of the nominal capacity during the first year and reaching 100% capacity from the second year onward.
The main product of the project is gold bullion, produced through an established industrial process for recovering gold from gold-bearing ores. To extract the gold contained in the ore, the material must first be crushed and then ground. This process is carried out using industrial crushers and ball mills, after which the material undergoes several processing stages to produce gold bullion.
The finely ground gold-bearing ore is introduced into a cyanide solution, where the gold dissolves and forms a gold-cyanide complex. The gold-cyanide complex is then adsorbed onto activated carbon and transferred to the gold room. In the final stage, gold and associated elements are separated through aqua regia treatment, and the recovered gold is converted into gold bars through a melting process.
The presence of suitable mineral resources in the project area and the possibility of exploiting these reserves using modern technologies in accordance with international standards will not only increase productivity and create greater added value in this sector, but, considering Iran’s position in terms of global gold consumption, will also contribute to reducing imports and foreign currency outflows.
Furthermore, implementation of the project will create numerous direct and indirect employment opportunities and provide more favorable conditions for investment in related industries. This will contribute, albeit to a limited extent, to reducing unemployment and creating effective demand in the local market for the supply of raw materials. It can also reduce income-related risks for young people in the region, strengthen self-reliance within urban communities, promote the development and application of advanced technologies in the country, and ultimately contribute to economic growth in the region.
Activities Undertaken for the Establishment of the Gold Recovery Plant
- Submission of the first edition of the project’s technical and economic feasibility report on April 6, 2021.
- Completion of the qualitative evaluation for the selection of the project’s EPC contractor and submission of the evaluation report on June 19, 2021.
- Preparation and submission of the draft tender documents for the selection of the EPC contractor on June 29, 2021.
- Preparation and submission of the basic engineering documents on July 4, 2021.
- Submission of the revised version of the project’s technical and economic report on September 7, 2021.
- Holding multiple meetings with the Investment Committee and Board of Directors of Sadr Tamin Holding.
AMT Electromagnetic Data Acquisition
Today, exploration for semi-deep and deep mineral deposits has become a priority for leading mineral exploration companies, particularly in light of rising metal prices. The Kharastan-Bidaster mineral area is considered one of the most unique mineral zones in terms of its geological and metallogenic characteristics.
Following the issuance of an exploration discovery certificate for gold and copper in this area, an exploration target for a porphyry copper deposit associated with intrusive bodies was defined.
The first step in exploring semi-deep and deep metallic deposits is the application of geophysical methods. Significant advances have been made in recent years in the development of modern technologies in this field. Electromagnetic surveying is one of the effective geophysical methods used for identifying such deposits and includes several specialized techniques.
The AMT (Audio-Magnetotelluric) method is one of these techniques. Due to its suitable accuracy and resolution, as well as its effective depth of investigation, AMT is particularly appropriate for this type of exploration.
In this regard, Pars Tamin Mining Development Company, following the publication of a public call for identifying contractors equipped with the appropriate instruments for this type of data acquisition, entered into a cooperation agreement with a multinational company operating across Iran, Turkey, Italy, and Canada. The data acquisition operation is currently being carried out by the Turkish team.
Exploration Activities Completed
Geotechnical Studies and Testing for the Gold Plant
- Mechanical drilling using the continuous core drilling method, along with SPT (Standard Penetration Test) at two-meter intervals and at layer changes.
- Drilling of six boreholes, each to a depth of 30 meters.
- Field plate load testing and in-situ density testing, followed by preparation and submission of the engineering report.
- Laboratory testing and preparation of the geotechnical engineering report.
- Field downhole seismic testing, along with preparation and submission of the engineering report.
Environmental Activities
- Obtaining environmental permits: Each stage required the preparation of detailed reports addressing the questions and requirements of the relevant authorities. In some cases, the reports prepared reached approximately 1,000 pages. These efforts resulted in obtaining four out of the five permits required for the final environmental approval. Subsequently, based on the requirements and formats specified by the Department of Environmental Protection, the final report was submitted to the relevant authority on Saturday, November 6, 2021.
- Holding five meetings at the company’s head office in Tehran with the plant construction consultant, mining consultant, and environmental consultant.
- Holding four in-person meetings with the Environmental Protection Management Company, attended by consultants from Pars Tamin Mining Development Company.
- Holding meetings with the project consultant and environmental consultant regarding the submission of reports in the format required by the environmental authorities.
- Approval of the capacity increase by the Environmental Protection Organization of Sistan and Baluchestan Province and submission of the approval to the national environmental authority.
- Preparation and submission of 1,600 pages of reports concerning project modifications.
- Holding a meeting of the National Article 2 Evaluation Committee on December 29, 2021.