76% progress of Taftan gold extraction plant
Muhammad Nabi Nouri, CEO of Pars Tamin Mining Development Company, announced that the Taftan Gold Recovery Plant Construction Project has reached 76% progress, presenting a report on the latest status of the project.
According to the Public Relations Department of Pars Tamin Mining Development Company, a weekly meeting was held with the participation of Amirhossein Naderi, CEO of Sadr Tamin Holding, and Nouri, CEO of Pars Tamin, to review the progress of the Taftan Gold Project. During the meeting, a report on the status of this major industrial project was presented.
At the meeting, Nouri announced that the Taftan Gold Recovery Plant Construction Project had achieved 76% progress.
Accordingly, the EPC process for the construction of the gold recovery plant at the Madofti Mine officially commenced on April 4, 2022.
Following the establishment of the project site, the contractor initially entered into an agreement with Newmax Company for technology transfer in the engineering phase. It then proceeded with obtaining the project’s basic design approvals before moving on to the detailed engineering phase.
According to the report, the detailed engineering phase began with priority given to the procurement of long-lead equipment to prevent delays in the project schedule. The engineering and procurement processes for the equipment were also initiated, and engineering documents such as datasheets and Material Requisitions (MRs) were prepared and submitted to the contractor’s procurement department.
The long-lead equipment includes crushers, ball mills, filter presses, compressors, pumps, diesel generators, thickeners, leaching tanks, and other equipment. The installation and commissioning of this equipment are currently being completed, and all major equipment has been delivered to the project site.
The report further states that, with the aim of preventing any difficulties during the execution phase and enabling the contractor to continuously allocate the necessary resources, the preparation of the project’s main structural and architectural drawings was placed on the agenda. The designs and construction of the foundations for the main equipment have also been completed at the site, and the foundations are currently ready for equipment installation.
It should be noted that installation activities are being carried out in parallel with the project’s structural engineering operations. It is hoped that the installation of the equipment will be completed as soon as possible, allowing the project to enter the pre-commissioning and commissioning phases.