Minister of Industry, Mines and Trade visits the largest gold factory in the east of the country
Seyed Mohammad Atabak, Minister of Industry, Mines and Trade, Mohammad Karami, Governor of Sistan and Baluchestan, Ali Kord, representative of Khash, Nosrat Abad, Mirjaveh and Korin provinces in the Islamic Consultative Assembly, accompanied by Mohammad Nabi Nouri, CEO of Pars Tamin Mines Development Company, visited the Taftan gold extraction factory.
Minister of Industry, Mines and Trade, while visiting the Taftan gold extraction factory, which belongs to Sadr Tamin Investment Company, one of the holdings of Shasta Group (a subsidiary of the Ministry of Cooperatives, Labor and Social Welfare), congratulated the arrival of the month of Rabi al-Awwal and said: A good factory has been built using provincial advantages, and God willing, the existence of this factory can improve the economic conditions in this province, which has many advantages.
He pointed out that environmental issues have also been taken into account in the construction of the Taftan gold extraction plant and added: “I believe that by expanding the provincial infrastructure, the attraction of investors for such value-creating activities that are also profitable for the country will definitely increase.”
Seyyed Mohammad Atabak called Sistan and Baluchestan province a rainbow of mines and stated regarding the prospects of this province with regard to its mining, commercial and industrial capacities: Sistan and Baluchestan has many advantages, both in the commercial sector, which is strengthened by its border with two densely populated countries, and in the mining sector, which has reserves of various elements.
He expressed satisfaction with the support of the governor and representatives for the series of measures that have been taken in the region and emphasized: “If in the future we can attract more investors in the mining sector to the region and this is also supported in the province and by the people, a bright future is expected for Sistan and Baluchestan.”
Sadr Tamin Holding (TASICO), as the largest and most strategic holding specialized in the mining and metal and non-metal mining industries, which is a subsidiary of the Social Security Investment Company (Shesta); with the approach of playing a pivotal role in the development and transformation of mining, completing the value chain in this area and increasing the quality of life of the people of the region, prioritized investment in the Taftan gold extraction plant construction project, and this project was implemented by Pars Tamin Mine Development Company, the executive arm of the holding.
Employment resulting from the entry of this industry into the region, in Sistan and Baluchestan Province as the largest gold project in the east of the country, has been 1,500 jobs, directly and indirectly, which was carried out in the early stages with priority to select and recruit local workers through employment tests, specialized interviews, and in the final stage, specialized training classes in theory and practice.
It should be noted that the next stage of the gold development plan in this province is the design of a gold processing and extraction plant with a production capacity of 5 tons of gold bars, which has been started and will be put into operation in 1406, and the second stage will follow with a production capacity of 5 tons of bars per year in 1409.
Taftan Gold Mine:
- Start of exploration studies: 2012
- Received mine discovery certificate: 2019
- Amount of exploration reserves: 100 million tons of ore with an average grade of 1.3ppm
Gold extraction plant:
- Received the license to build the Taftan gold extraction plant: 2011
- Goal: Production of gold bullion, regional development, creation of security and employment
- Key features: All-Iranian indigenous design, engineering and equipment in the largest gold production project in the east of the country
- Input feed: Annual input of 190 thousand tons of ore
- Production capacity: Initial annual production capacity of 500 kilograms of gold bullion
- Project start date: May 2011
- First firing and hot test: Winter 2023
- Factory construction period: 20 months
- With an investment of $55 million
- Capacity increase in the second phase by 1020 Kilograms of annual gold bullion production on the horizon